FirstEnergy keeping 3 old Ohio coal plants running

Emiratesvoice, emirates voice

Emiratesvoice, emirates voice FirstEnergy keeping 3 old Ohio coal plants running

Washington - Arabstoday

A US power grid operator has asked FirstEnergy Corp to keep running three coal-fired plants in Ohio that generate about 885 megawatts in an effort to maintain a reliable supply of electricity, the company said. PJM, the grid operator for 13 U.S. Mid-Atlantic and Midwest states, asked for reliability-must-run arrangements for the 132-MW Units 1-3 at the Eastlake plant, the 244-MW Ashtabula 5 and 245-MW Lake Shore 18, FirstEnergy told investors after its earnings report this week. The plants had been earmarked for retirement this year. FirstEnergy spokesman Mark Durbin said on Thursday that the plants would be available until April 2015 when the U.S. Environmental Protection Agency\'s (EPA) Mercury and Air Toxics rules are due to be implemented. He could not discuss terms of the must-run contracts. In January, FirstEnergy told PJM that it wanted to shut this year about 2,700 MW of smaller, older coal units in Ohio, Pennsylvania and Maryland, most of which had entered service in the 1950s and 1960s. FirstEnergy said it wanted to retire the old plants because it did not make economic sense to upgrade the units\' emissions equipment to meet more-stringent federal environmental rules proposed over the past couple of years. FirstEnergy is not alone in shutting small, older coal plants. Energy companies across the United States have announced planned shutdowns of more than 30,000 MW of coal-fired power plants due to the stricter environmental rules, low natural gas and power prices and weak economic and power demand growth, among other factors. Separately, FirstEnergy said it had filed with PJM in March to interconnect a proposed 800-MW natural gas and oil-fired, combustion turbine peaking plant at the Eastlake facility to help ensure reliable electric service in the area in the future. FirstEnergy did not say how much the turbines would cost, but it said if PJM allows the interconnection and FirstEnergy decides to go ahead with the project, the turbines could enter service in 2015 when the EPA\'s mercury rules take effect and the coal units with the reliability-must-run contracts shut. FirstEnergy owns nearly 23,000 MW of generating capacity and supplies power to 6 million customers in Ohio, Pennsylvania, New Jersey, West Virginia, Maryland and Virginia.

Name *

E-mail *

Comment Title*

Comment *

: Characters Left

Mandatory *

Terms of use

Publishing Terms: Not to offend the author, or to persons or sanctities or attacking religions or divine self. And stay away from sectarian and racial incitement and insults.

I agree with the Terms of Use

Security Code*

firstenergy keeping 3 old ohio coal plants running firstenergy keeping 3 old ohio coal plants running

 



Name *

E-mail *

Comment Title*

Comment *

: Characters Left

Mandatory *

Terms of use

Publishing Terms: Not to offend the author, or to persons or sanctities or attacking religions or divine self. And stay away from sectarian and racial incitement and insults.

I agree with the Terms of Use

Security Code*

firstenergy keeping 3 old ohio coal plants running firstenergy keeping 3 old ohio coal plants running

 



GMT 10:18 2016 Wednesday ,23 March

cartoon seven

GMT 10:31 2014 Tuesday ,23 December

Mirages of failure: Lebanon cannot wait

GMT 05:14 2024 Wednesday ,07 February

Sophisticated Classic Dining Room Design Ideas

GMT 09:18 2018 Thursday ,11 January

As US freezes aid, Pakistan dismisses economic fears

GMT 06:01 2018 Thursday ,04 January

Etihad Aviation Group celebrates 2018

GMT 12:51 2017 Thursday ,11 May

Suspected killer of Hamas commander arrested

GMT 22:29 2017 Saturday ,24 June

Bahrain committed to Islam’s

GMT 19:43 2017 Friday ,21 July

Iran provided weapons, training for attacks

GMT 12:20 2012 Saturday ,23 June

Batista to sell $2 bln gold venture to Qatar

GMT 12:31 2012 Friday ,21 September

Dubai Ports give up Aden Port for $27 million

GMT 06:42 2011 Friday ,12 August

Google+ social network adds games

GMT 06:22 2013 Wednesday ,25 September

Samsung launches Galaxy Note 3 in 58 countries

GMT 01:00 2016 Tuesday ,29 November

Time to discuss new prospects

GMT 14:14 2011 Wednesday ,13 July

Ethiopia :4.5 million people need food aid
 
 Emirates Voice Facebook,emirates voice facebook  Emirates Voice Twitter,emirates voice twitter Emirates Voice Rss,emirates voice rss  Emirates Voice Youtube,emirates voice youtube  Emirates Voice Youtube,emirates voice youtube

Maintained and developed by Arabs Today Group SAL.
All rights reserved to Arab Today Media Group 2025 ©

Maintained and developed by Arabs Today Group SAL.
All rights reserved to Arab Today Media Group 2025 ©

emiratesvoieen emiratesvoiceen emiratesvoiceen emiratesvoiceen
emiratesvoice emiratesvoice emiratesvoice
emiratesvoice
بناية النخيل - رأس النبع _ خلف السفارة الفرنسية _بيروت - لبنان
emiratesvoice, Emiratesvoice, Emiratesvoice