Only 56 days are left to finalize the new Suez Canal Project, the Armed Forces said on Thursday.
Dry digging operations at the New Suez Canal were over after digging 230 million cubic meters, the army said in a statement.
It added that further 50 million cubic meters have been dug to expand El Ballah bypass to become 10 kilometers long and 312 meters wide.
A total of 217 million cubic meters of water-saturated sand have so far been lifted at the New Suez Canal project.
The figure represents 84.1 percent of the target of 258 million cubic meters.
About 38 dredgers are operating in the water way.
Four tunnel groups with each group consisting of two tunnels are now being built, including car and train tunnels, the statement said
GMT 00:37 2018 Wednesday ,24 January
Bitcoin slumps below $10,000GMT 22:49 2018 Tuesday ,23 January
Sharjah apartment rents see steep decline in 2017GMT 19:15 2018 Tuesday ,23 January
Emirati fined Dh2.2m for embezzling public fundsGMT 22:27 2018 Monday ,22 January
Jafza bridge benefits trade, logistics supply chainGMT 22:21 2018 Monday ,22 January
Damac chairman to speak on digital skillsGMT 10:55 2018 Monday ,22 January
Bahrain-Indian economic ties discussedGMT 22:42 2018 Saturday ,20 January
'Massive' infrastructure spending needed in AfricaGMT 12:49 2018 Tuesday ,16 January
Tabarak Buys Majority Stake in a Private Company

Maintained and developed by Arabs Today Group SAL.
All rights reserved to Arab Today Media Group 2025 ©
Maintained and developed by Arabs Today Group SAL.
All rights reserved to Arab Today Media Group 2025 ©
Send your comments
Your comment as a visitor