
The world's largest dredging project is close to an end as only 25 days left for inaugurating the New Suez Canal project.
A total of 250.324 million cubic meters of water-saturated sand have so far been lifted at the new Suez Canal project, a report issued by the project's executive administration said on Saturday.
The figure represents 95.45 percent of the target of 258 million cubic meters, the report added.
Currently, 33 dredgers are operating in the project's three sectors, the report said.
The enlarged Suez Canal will allow ships to sail in both directions at the same time over much of the canal's length. This is expected to decrease waiting hours from 11 to 3 hours for most ships and to double the capacity of the Suez Canal from 49 to 97 ships a day.
Revenues from the Suez Canal would jump from 5 billion dollars to 12.5 billion dollars annually.
The construction of the new canal was initially scheduled to take five years. It was then first reduced to three years and finally ordered by President Abdel Fattah el-Sisi to be completed in only one year.
GMT 00:37 2018 Wednesday ,24 January
Bitcoin slumps below $10,000GMT 22:49 2018 Tuesday ,23 January
Sharjah apartment rents see steep decline in 2017GMT 19:15 2018 Tuesday ,23 January
Emirati fined Dh2.2m for embezzling public fundsGMT 22:27 2018 Monday ,22 January
Jafza bridge benefits trade, logistics supply chainGMT 22:21 2018 Monday ,22 January
Damac chairman to speak on digital skillsGMT 10:55 2018 Monday ,22 January
Bahrain-Indian economic ties discussedGMT 22:42 2018 Saturday ,20 January
'Massive' infrastructure spending needed in AfricaGMT 12:49 2018 Tuesday ,16 January
Tabarak Buys Majority Stake in a Private Company

Maintained and developed by Arabs Today Group SAL.
All rights reserved to Arab Today Media Group 2025 ©
Maintained and developed by Arabs Today Group SAL.
All rights reserved to Arab Today Media Group 2025 ©
Send your comments
Your comment as a visitor