It is the biggest contract Spanish firms have ever undertaken abroad, a high-speed railway linking Islam's holiest cities, Mecca and Medina, in Saudi Arabia -- but sand is covering the tracks and now the building partners are arguing over who should clean it up.
Spanish construction and engineering firm OHL, one of the companies behind the project, refuses to remove sand for free in a letter sent to its consortium partners which was published Tuesday by news site El Confidencial.
In 2011, Saudi Arabia awarded the contract worth 6.7 billion euros ($7.4 billion) to the consortium of 12 Spanish companies and two Saudi firms for a project which aims to improve transport connections during the annual hajj pilgrimage.
The contract is for laying the 444 kilometres (275 miles) of track between the two cities as well as supplying 35 trains and operating and maintaining the line for 12 years.
The leading firms in the consortium –- train maker Talgo, state-run train operator Renfe and state track operator Adif – have extensive experience with Spain's own high-speed network, the world's second largest after China's.
The Saudi project is the first such line to be built across a desert. The rail line crosses the Arabian Desert, where sandstorms are frequent and large dunes can suddenly form.
In a copy of the letter dated February 7 which was seen by AFP, OHL said it was not "paid to clear the track of sand in order to facilitate the work of other consortium members."
Talgo wants to start test runs of its trains on the track.
OHL said it was "very willing to carry out extra works to clear the tracks" but only after an agreement with the other members of the consortium is signed spelling out what its exact responsibilities would be.
OHL declined to comment on the publication of the letter.
Public Works Minister Ana Pastor, who visited the work-in-progress in 2014, downplayed the row.
"We knew from the beginning what we would find. This is not a new question and it is up to Spanish engineers to solve this challenge," she told reporters.
The high-speed railway was initially scheduled to open at the end of 2016 but the deadline for its completion has been moved to the end of 2017.
GMT 00:37 2018 Wednesday ,24 January
Bitcoin slumps below $10,000GMT 22:49 2018 Tuesday ,23 January
Sharjah apartment rents see steep decline in 2017GMT 19:15 2018 Tuesday ,23 January
Emirati fined Dh2.2m for embezzling public fundsGMT 22:27 2018 Monday ,22 January
Jafza bridge benefits trade, logistics supply chainGMT 22:21 2018 Monday ,22 January
Damac chairman to speak on digital skillsGMT 10:55 2018 Monday ,22 January
Bahrain-Indian economic ties discussedGMT 22:42 2018 Saturday ,20 January
'Massive' infrastructure spending needed in AfricaGMT 12:49 2018 Tuesday ,16 January
Tabarak Buys Majority Stake in a Private Company

Maintained and developed by Arabs Today Group SAL.
All rights reserved to Arab Today Media Group 2025 ©
Maintained and developed by Arabs Today Group SAL.
All rights reserved to Arab Today Media Group 2025 ©
Send your comments
Your comment as a visitor