Up to 174.865 million cubic meters of water-saturated sand have been dredged so far as part of the Suez Canal Development Project.
This represents 67.8 percent of a total 250 million cubic meters that should be dredged as part of the project.
Thirty-nine dredgers are working in the project, said Wagdi Zaki, the executive director supervising the dredging process, Tuesday.
About 1.475 million cubic meters of water-saturated sands were dredged Monday, Zaki said.
The project aims at expanding the Suez Canal region's role as a global, industrial, and logistics center that is environmentally balanced with an integrated economy.
It is also projected to become a global hub due to its logistics and industrial services.
The project was funded through granting investment certificates to Egyptians with 12% returns, and in eight days, more than 60 billion pounds were collected.
GMT 00:37 2018 Wednesday ,24 January
Bitcoin slumps below $10,000GMT 22:49 2018 Tuesday ,23 January
Sharjah apartment rents see steep decline in 2017GMT 19:15 2018 Tuesday ,23 January
Emirati fined Dh2.2m for embezzling public fundsGMT 22:27 2018 Monday ,22 January
Jafza bridge benefits trade, logistics supply chainGMT 22:21 2018 Monday ,22 January
Damac chairman to speak on digital skillsGMT 10:55 2018 Monday ,22 January
Bahrain-Indian economic ties discussedGMT 22:42 2018 Saturday ,20 January
'Massive' infrastructure spending needed in AfricaGMT 12:49 2018 Tuesday ,16 January
Tabarak Buys Majority Stake in a Private Company

Maintained and developed by Arabs Today Group SAL.
All rights reserved to Arab Today Media Group 2025 ©
Maintained and developed by Arabs Today Group SAL.
All rights reserved to Arab Today Media Group 2025 ©
Send your comments
Your comment as a visitor